Beverage Filling Machine FAT: Agree the Test, Keep the Evidence

A factory acceptance test checks the agreed machine configuration before shipment. A useful result links each requirement to a defined test and a retained record; it is not just a short running video. Agree the materials, conditions, measurement method and limits first, and mark what must still be verified with the real product or at the installation site.

Prepare My FAT Inputs

Machine selection and configuration

FAT protocol inputs

  • Approved machine scope and drawings
  • Bottle, cap and test-product basis
  • Utilities and supply conditions
  • Test duration and output definition
  • Fill level or volume sampling plan
  • Closure checks and reject handling
  • Alarm, interlock and recovery checks
  • Changeover and cleaning demonstration
  • Documents, photos, videos and open-item register

Machine selection and configuration

Example: Gross Speed Is Not Accepted Output

Illustrative arithmetic only—not a machine rating, an actual customer FAT or a recommended test duration. This example keeps all stops inside the same 30-minute window; agree the time boundary before your test.

RecordExample valueWhat it establishes
Elapsed observation window30 minutes = 0.5 hourIncludes the stops recorded within this example window
Counted filled bottles3,100Gross observed rate: 3,100 / 0.5 = 6,200 BPH
Rejected bottles40Record the cause; a filled bottle is not automatically an accepted bottle
Accepted bottles3,100 - 40 = 3,060Accepted output: 3,060 / 0.5 = 6,120 BPH
DecisionCompare the agreed limits and all other testsThe arithmetic alone does not authorize a pass or shipment release

Machine selection and configuration

Match the Demonstration to the Product Claim

ApplicationProduct-specific evidence to agreeWhat a water-only run cannot establish
Still waterApproved package, accepted output, fill measurement and closure checksPerformance on every other bottle or recipe
Carbonated drinkActual test-liquid basis, inlet condition, CO2 measurement and foam/reject recordsCarbonation retention and losses at your operating conditions
Hot-filled juice or teaAuthorized thermal sequence, actual package trial and defined product substitute limitsValidated thermal treatment, package resistance or shelf life
Pulp, particles or viscous productRepresentative product properties and an agreed valve/handling trialParticle passage, viscosity behavior or filling consistency of the actual recipe

Machine selection and configuration

A usable FAT record: pass, fail or open

Set the limits in the purchase specification before the run. These rows define evidence to collect, not universal acceptance thresholds.

CheckRecord during the testDecision to agree in advance
Sustained outputStart/end timestamps, gross count, accepted count and every stopWhether rate is gross or accepted bottles and how interruptions affect the test
Fill consistencySample IDs, measured amount/level, product temperature, instrument and calibration recordSampling frequency, measurement method and upper/lower limits for this product
Bottle and cap handlingJam, scuff, cap application and leak-check observationsApproved drawings/samples and closure-specific inspection method
Controlled stop and restartStop cause, product disposition, restart sequence and rejected bottlesSafe response and recovery procedure for the specified machine
ChangeoverFrom/to formats, elapsed time, tools, parts and first accepted bottleWhat is included in changeover time and how the next format is verified
Open itemsUnique ID, severity, owner, due date and closure evidenceWhich defects prevent shipment and which require a documented retest

Machine selection and configuration

Connect factory testing to site acceptance

State what the test product proves

A water trial does not by itself demonstrate juice viscosity, particulate handling, hot-fill performance or carbonation retention. Record every substitute material and carry unresolved product-specific tests into an agreed verification plan.

Preserve the signed test evidence

Keep the approved configuration, dated protocol, measured results, instrument records, videos and open-item register together. A single short video cannot show sustained operation, reject rate or all alarm responses.

Plan the site acceptance boundary

Site acceptance checks the delivered machine with actual utilities, upstream/downstream equipment and operators. Define these conditions before shipment and distinguish site-integration issues from factory-test results.

Plan the site acceptance boundary

Machine selection and configuration

Keep the Shipment Decision Separate from a Test Demonstration

Use these as protocol fields, not universal contractual release rules. The buyer and supplier agree who may approve each outcome.

OutcomeRequired recordNext action
Pass on the tested scopeRequirement ID, measured result, evidence reference and sign-offRetain the record and identify any tests that remain site-dependent
Failed acceptance requirementDeviation, affected scope, corrective action and retest evidenceFollow the agreed hold/retest rule before release
Not tested or substitute conditionsReason, limitation, test owner and next verification stageDo not label an untested capability as passed

Machine selection and configuration

Carry the Same Requirements into the Next Stage

Engineering decision guide

Continue the buyer decision path

Use these pages in sequence to understand, compare, plan, choose and prepare a project-specific request.

  1. Beverage Filling Machines

    Compare filling machine families by beverage behavior, filling basis, package handling and the interfaces required around the filler.

  2. Filling Technology Comparison

    Compare gravity, hot-fill and isobaric routes against the same product, package, acceptance and cleaning facts.

  3. Filling Machine Factory Acceptance Test

    Write FAT conditions, materials, duration, sample method, acceptance criteria, records and deviation handling before the test.

  4. Filling Machine Selector

    Generate a preliminary technology route from beverage, process, package and output inputs, then verify open assumptions with an engineer.

  5. Request a Filling Machine Recommendation

    Send a structured machine brief with the known product, package, output, site and project facts, while marking unknowns openly.

Buyer questions

Frequently asked questions

What makes a filling-machine FAT result pass or fail?

The approved protocol must define the test materials, duration, output, sampling, fill and closure criteria, demonstrations, records and open-item closure rule.

Does a successful water trial prove my carbonated or hot-fill process?

No. Record what the substitute test liquid and factory conditions demonstrate, and which product-specific requirements remain untested. Agree separate evidence for carbonation, thermal processing, particle handling or package resistance as applicable. A factory trial is not a universal process or shelf-life validation.